| My sister Rebecca and Alexia out front. On the way home from Thanksgiving in New Mexico, we stopped and checked on the progress. The builders had started framing the house. |
| December 7, 2012 - I was in Tempe checking out locations for a client and since I was halfway there, drove the rest of the way with Spencer to see the house. |
From: ray.wisinski@lennar.com
Date: Wed, 12 Dec 2012 15:52:23 -0600
To: <hdhstew@gmail.com>
Subject: Hello Darren and Heidi
Hello,
Just wanted to let you know that they have put up the scaffolding
around your home. They will be installing the Lathe on the exterior very
soon. They also were working on some of the water lines today. Your
home is coming along very well.
Hope you are all doing well.
Kindest Regards,
Ray
| December 16, 2012 - Darren's parents came for visit and we drove up and walked through the model and our house with them. They are so excited for us! |
From: ray.wisinski@lennar.com
Date: Mon, 7 Jan 2013 17:19:42 -0600
To: <hdhstew@gmail.com>
Cc: <todd.bruns@lennar.com>
Subject: Happy New Year
Hello Darren and Heidi,
I apologize for not communicating for the last two and one half weeks, I have been on vacation.
Hopefully you had a wonderful Christmas. The children always do, and no
matter our ages, Christmas brings the child out in all of us.
Your home has gone to dry wall, and this process of hanging the dry
wall, taping, mudding, texturing and sanding typically takes about
eleven days to complete before they paint your interior. Once they
accomplish these tasks, they will install cabinets. Flooring (tile)
comes next. Your home, if all goes well, could be sixty to sixty-fives
out from completion. We can still not give you an exact completion date
yet, but as soon as we know, either Todd or myself will contact you.
Please let us know if there are any questions you may have as they
arise.
Happy New Year!!!
Kindest regards,
Ray
From: ray.wisinski@lennar.com
Date: Tue, 29 Jan 2013 17:48:06 -0600
To: <hdhstew@gmail.com>
Subject: Construction Update
Hello Darren and Heidi,
Hope all is well.
Since last week they did painting in your home. In addition they
started to install cabinets in your home. When I walked into the
kitchen...it looked awesome. Please let me know if there is anything
that Todd or I can assist you with.
Kindest Regards,
Ray
And while I was on my trip, Darren received this one:
Hello Darren and Heidi,
We just received the March
closing dates yesterday. Typically you should have received the official
mailing for the close dates in the mail. So I am happy to report that
you have your NHO walk through on 3/12/13 at 9:00am. That is when you will meet your construction manager and review all the mechanical systems throughout the home.
Your title appointment will be attached to the official mailing. Your Final walk or Celebration will be on 3/19/13 at 1:00pm. That will be at your home to finalize the issues on your first NHO walk.
Exciting times for sure.
Please let me know if you have any other questions. I am sure UAMC will
be contacting you shortly, if not, please let me know.
Kindest Regards,
Ray